|
introduction / existing floodway / need
for project / options considered / range
of alternatives / proposed floodway expansion / separate
project components / winnipeg flood improvements / recreational
facilities
A
word from the Environmental Assessment Study Team regarding Project
Description for the Floodway Expansion Proposal
This
Project Description is not considered complete at this
stage of the environmental assessment and engineering design. A major
effort of the Study Team will focus on building a detailed Project
Description for this Proposal. The refinement of the design of Project
components is currently ongoing and will be influenced by:
- Environmental
Assessment Studies
- Socio-Economic
Assessment
- Public
Opinions derived from Public Consultations,
- Other
Public Meetings, and;
- Engineering
design and performance optimizations.
The Project
Description is expected to evolve as the engineering design evolves
in response to information resulting from ongoing assessments and consultations.
Additional details regarding Project Description will be provided as
they beccome
available.
Introduction
The Government of Manitoba has established the Manitoba Floodway Expansion
Authority (MFEA) charged with the responsibility of executing a proposed
expansion of the existing Red River Floodway (Floodway) that exists to
protect the City of Winnipeg from catastrophic damage in the event of
extreme flooding events. The Red River Flood of 1997 resulted in water
levels that took the existing Floodway to the limits of its existing
design. Following the 1997 event, various levels of government initiated
a series of meetings and commissioned engineering studies to assess vulnerabilities
to flood damage and preferred options for providing a major increase
in flood protection for the City of Winnipeg.
introduction / existing
floodway / need for project / options
considered / range of alternatives / proposed
floodway expansion / separate project components / winnipeg
flood improvements / recreational facilities
Existing
Floodway

The
existing Red River Floodway Control Structureand
Channel during the 1997 Red River Flood.
The existing Floodway is a
flood diversion channel that was constructed between 1962 and 1968
as a major element of a coordinated flood-defence
response to massive damage incurred by the City of Winnipeg during the
1950 flood. After the 1950 flood, the Greater Winnipeg Diking Board was
established and began construction of a system of dykes to provide a
measure of protection against flooding within the City of Winnipeg. This
initial effort resulted in the construction of boulevard dykes and installation
of pumping stations to lift runoff into the rivers and outside the dykes
in low-lying areas. A series of “borrow” sites were also
established so material could be readily accessed to raise dykes in the
event of future flooding emergencies.
In 1958, a Royal Commission on Flood-Cost Benefit reported its recommendations
based upon a major study to assess structural solutions to flooding problems
on the Red and Assiniboine Rivers. As a result of this Commission’s recommendations,
three projects were built within the period between 1962 and 1972:
- Red River Floodway to divert 1700 cubic metres per second from the
Red River south of Winnipeg to the east of the city, discharging
this flow
back into the Red River at Lockport (project completed in 1968);
- a 700 cubic
metre per second capacity diversion channel to convey floodwaters
from the Assiniboine River immediately upstream of Portage la Prairie
northward to Lake Manitoba (completed in 1970);
- the Shellmouth Dam in the upper reaches of the Assiniboine River
just north of Russell (completed in 1972) to store floodwaters
and reduce
flow peaks downstream.
The existing Red River Floodway is a system consisting of four components:
the floodway channel, the inlet control system, the dykes, and the outlet
structure. The floodway channel is 48 kilometres long and drops in elevation
5 metres over the distance between the inlet and outlet. The designed
depth of flow within the channel is 8 metres. The width at the top of
the channel varies from 213 metres to 305 metres. Material excavated
from the channel was deposited along the side of the channel to form
embankment 6 metres high.
The entrance to the floodway is located in the eastern bank of the
Red River near St. Norbert. An earth-fill weir at the entrance
ensures that
flows below flood level continue down the Red River, and ensures that
ice floes do not enter the floodway channel.
The inlet control structure is located on the Red River just downstream
from the floodway inlet. The purpose of the control structure is to
regulate the flow between the natural channel of the Red River and
the floodway
channel, during the period of high water levels. The gates of the control
structure are normally in a submerged position with about 1.8 metres
of water over them in the summer months.
To prevent floodwaters from bypassing the inlet control structure,
dykes have been constructed on either side. On the east side of the
Red River,
the dyke is incorporated into the floodway embankment. To the west
of the Red River, the dyke extends for 34 kilometres from the inlet
control
structure to a point where the natural ground is above the design
flood elevation. During the 1997 flood, the dyke was raised and extended
an additional 25 km to prevent floodwaters from bypassing the structure
and entering the city.
The drop over the entire reach of the floodway is 5 metres, but the
corresponding drop of the Red River is 10 metres. The purpose of
the outlet structure
is to dissipate the energy in the water at its point of re-entry
to the Red River near Lockport, thereby preventing damage and erosion
in the
river.
introduction / existing
floodway / need for project / options
considered / range of alternatives / proposed
floodway expansion / separate project components / winnipeg
flood improvements / recreational facilities
The Need for Improved Flood Protection for the City of Winnipeg
The Floodway was designed
45 years ago to provide Winnipeg with protection up to an estimated
flood magnitude that would be exceeded once in 160
years, based on statistical data on river floods that existed at that
time. Recent recalculation of flood frequencies considering the past
40 years of flood data, a period that experienced a series of relatively
large floods (in 1966,1974,1979,1996 and 1997) reveal that the design
flood established in the 1960’s actually would represent only a
1 in 90 year flood event. Analyses of the historical record reveal that
large flood events can occur more frequently than were calculated using
the old (pre-1960’s) data.

The Floodway
Channel under 1997 Flood conditions.
Flood control works on the Red and Assiniboine Rivers have been extensively
used since their completion. Floods occurred on the Red River in 1969,
1970, 1974, 1979, 1987 and 1997. The 1979 flood was similar in magnitude
to the devastating flood of 1950, which was the catalyst for the construction
of these works. In 1997, a flood surpassed only by the 1826 flood of
record occurred on the Red River. This event served to demonstrate
yet again the enormous value of the flood control works to the
City of Winnipeg
and, at the same time, to emphasize the likelihood that a flood of
even greater magnitude could occur. Costs incurred by damages
to the City
of Winnipeg under the “do-nothing” scenario in the event
of a flood event larger than the 1997 flood would dwarf the cost of
expanding the existing floodway system. The City of Winnipeg has benefited
enormously from the establishment of the Red River Floodway and the
overall flood protection system, where serious flooding has been avoided
since
control works went into operation. Potential damages prevented during
the 1969 to 1991 period are in excess of $1.1 billion (in 1998 dollars)
in Winnipeg alone. The damages prevented in 1997 are significant. In
the absence of these works, a large area of the City would have been
inundated, hundreds of thousands of people would have been evacuated,
and the economic centre of Manitoba would have been completely paralyzed.
The cost of the Red River Floodway, Portage Diversion and Shellmouth
Reservoir totaled $94 million when constructed, or about $416.6 million
in 1998 dollars. It is clear that these flood control works have been
extremely cost effective.
introduction / existing
floodway / need for project / options
considered / range of alternatives / proposed
floodway expansion / separate project components / winnipeg
flood improvements / recreational facilities
Options Considered for Improved Flood Protection
Chronology
Following the 1997 Red River
Flood, President Bill Clinton and Prime Minister Jean Chretien asked
the International Joint Commission (IJC)
to study the flood and its impacts. In June of 1997, the Canadian and
American governments charged the IJC with examining and reporting on
the causes and effects of damaging flood events in the Red River, and
to make recommendations on means to reduce, mitigate and prevent harm
from future flooding in the Red River Basin. In September of 1997, the
IJC established the International Red River Basin Task Force to examine
a range of alternatives to prevent future flood damage. This Task Force
undertook and commissioned a series of studies and in 1999 commissioned
a study on flood risks in Winnipeg and possible means to reduce those
risks. Reports from the study were submitted to the IJC Task Force in
1999 and in 2000.
Reports to International Joint Commission (IJC)
The reports submitted to IJC contained several major findings:
- Winnipeg is at risk to major floods of the magnitude of the 1997 flood,
or larger
- Many vulnerabilities exist that should be improved
- Potential damages to Winnipeg due to floods exceeding the 1997 Flood
event would be as much as $17 Billion for a 1 in 1000 year flood.
- The preferred options to provide a major increase in flood protection
were the St. Agathe Detention Structure or the Floodway Expansion.
introduction / existing
floodway / need for project / options
considered / range of alternatives / proposed
floodway expansion / separate project components / winnipeg
flood improvements / recreational facilities
Range of Alternatives Considered
While the Reports to IJC in 1999 and 2000 led to the identification
of two preferred options for improved flood protection, a wide range
of alternatives were explored. These alternatives included:
- Channel improvements in the Red River in Winnipeg and in the river reach
north of Winnipeg to increase discharge capacity of the river.
Diversion of the eastern tributaries of the Red River (including
the Roseau River, Rat River, Joubert Creek, Cook’s Creek, etc.) around
the city to re-enter the Red River north of the existing Floodway outlet.
A detention structure on the Red River upstream of Winnipeg near
St. Agathe where some of the flood waters of the Red River
would be detained
temporarily during an extreme flood to reduce the outflow through
the Winnipeg area, at the cost of incremental flooding upstream.
Raising of the primary dykes in Winnipeg on a permanent basis
to permit more flow to safely pass through the river during
a flood.
Installation of a massive pumping plants at the inlet to
the floodway to mobilise the large discharge capacity of
the Floodway
at high water
levels, without actually having to raise the water level
upstream of the Floodway inlet above the ”State of Nature” level.
Increase the freeboard on the West Dike and modify the
operation rules of the Floodway to permit more frequent
and higher
water levels upstream
of the Floodway inlet.
Remove a portion of the East Embankment of the Floodway
to permit more efficient entrance of floodwater into
the Floodway,
thereby
increasing
its discharge capacity.
Removal of the Outlet Control structure on the Floodway.
Removal of the entrance weir at the inlet to the Floodway.
Raise the bridges along the Floodway channel to increase
the hydraulic capacity at high water levels.
Construct a “twin” floodway adjacent to the existing channel
to increase the discharge capacity of the diversion. The possibility
of extending this channel north of the current outlet location was also
considered.
Construct a separate Floodway Channel to the
west of Winnipeg.
Increase the capacity of the Portage Diversion,
thereby reducing the potential for the Assiniboine
River
to intensify flood
levels in Winnipeg.
Increase the height of the Shellmouth Dam
to develop more storage capacity that could
further
reduce
the contribution of flood
from the Assiniboine
River.
Expand the existing Floodway to increase
its discharge capacity, and continue
with the existing
operation
rules.
While all these alternatives were considered, not all options were analysed
rigorously because cursory review was adequate to show that some option
were clearly uneconomic, had only minor hydraulic benefits, or had environmental
impacts that would be unmanageable or almost certainly unacceptable.
At the request of the IJC, the consideration of alternatives did not
consider the option of developing storage reservoirs upstream in the
Red River watershed, as the IJC Task Force was evaluating this option
in a separate process. In Novermber, 2000, the IJC concluded in its own
process that it would be both economically and environmentally infeasible
to produce enough acceptable large reservoir storage that alone would
reduce substantially the flood peaks for major floods.
Subsequent to the release of the 1999 and 2000 reports, the Province
of Manitoba retained KGS Group to carry out further study of the two
preferred options that had emerged from the studies commissioned by
the IJC. The Report generated from this study was released in
November, 2001.
The Report described the costs and impacts of both schemes, without
selecting a preferred option. The selection between the two options
was deemed
by the consultant to be of major social significance to Manitoba, and
opted to yield a decision on selecting a preferred option to the provincial
government on behalf of the citizens of Manitoba. The Province of Manitoba
selected the Floodway Expansion option as the preferred option.
introduction / existing
floodway / need for project / options
considered / range of alternatives / proposed
floodway expansion / separate project components / winnipeg
flood improvements / recreational facilities
The Proposed Floodway Expansion
A finalised version of the project description for the
proposed Floodway Expansion project does not yet exist. The concept continues
to undergo refinement as results from ongoing studies become available.
Consequently the designs will continue to evolve and undergo optimization
as additional information is acquired. Studies currently underway to
define the project in more detail include environmental impact assessments,
re-engineering of bridge and utility crossings, drainage works and other
engineering components not yet in the final design stage. In fact, the
design of the Floodway Expansion itself is expected to evolve in response
to issues identified in both the environmental assessment and public
consultation processes which are currently underway. While complete engineering
design is not yet finalised, sufficient detail does exist to offer conceptual
detail of the main components of the proposed Floodway Expansion Project.
Project Components
The existing floodway diverts a limited volume of flow
from Red River floodwaters around the City of Winnipeg using a system
comprised of a gate control structure and the Floodway Channel. Spring
runoff flood events are controlled by raising the control gates at the
gate control structure, limiting Red River flow through the channel passing
through the City of Winnipeg. Flow is diverted upstream of the control
structure to the entrance of the Floodway Channel, where the flow is
routed around the City of Winnipeg. Flow from the Floodway Channel re-enters
the Red River via an engineered outlet structure located north of Lockport.
While the current Floodway configuration provides protection to the
City of Winnipeg from floods with a 1 in 90 years probability
of reoccurrence,
this level of protection was determined to be barely adequate for a
larger magnitude flood such as the Flood of 1997, which was a
1 in 100 year
flood event. The Proposed Floodway Expansion will increase protection
for the City of Winnipeg from a 1 in 90 year flood to a 1 in 700 year
flood event, primarily through deepening and widening of the existing
Floodway channel.
The Proposed Manitoba Red River Floodway Expansion Project consists
of upgrades and enhancements to several components of the existing
flood
control works and Floodway diversion system. Detailed information
about each of these enhancements will be provided during this
assessment
process once designs become more fully evolved. At this juncture,
a general description
of the enhancements and upgrades includes the following:
- Modifications to 13 existing railway and highway bridges,
five transmission lines, other crossings, seven drainage structures,
and the excavation of approximately 35 million cubic metres of soil for
Floodway channel widening and deepening.
- Upgrades to the inlet control structure, including a fire protection
system, installation of additional riprap and erosion control measures
to protect the embankments of the control structure.
- Increases in elevation of the west dike and raising a portion of
the Floodway channel adjacent to the inlet control structure
- Widening of the outlet structure and the discharge channel to the
Red River. River bank stability and erosion in the Red River
north of the
Floodway outlet will also be addressed in this upgrade.
- Enlargement of the Floodway Channel by varying amounts along its
46 km (29 miles) length, with width increases up to approximately
110
m (360 ft), and depth increases
up to 2 m (6.5 ft), subject to final design optimization. The total volume
of excavation is estimated to be 34 million cubic metres (45 million
cubic yards).
The new design capacity will be 3960 m3/s (140,000 cfs), compared to the
original design capacity of
1700 m3/s (60,000 cfs) used in the 1960’s.

Hydro
transmission line crossings are one of several services crossing
the Floodway Channel.
Specifically, separate upgrades are anticipated to consist of the following:
- Increase in the freeboard
at the existing West Dike that extends over 70 km (44
Miles) from the Floodway Inlet Control Structure in a generally south
westerly direction to tie into high ground at the west side
of the Red River Valley. The dike will be increased
in height by varying amounts estimated to be up to 1.2 m (4 ft) and
the west end will be
extended beyond the current location. The dike is currently considered
to provide
acceptable safety against wind effects on the floodwaters of the Red
River for water levels up to El 236 m (El 774 ft) at the Floodway
Inlet Control Structure. In its improved
condition, it is intended to be capable of safely protecting against
water levels up to El
237 m (El 778 ft) at that location.
- Modification of the bridges over the Floodway Channel. This will
consist of a
combination of outright replacement of some of the bridges, and retrofitting
of others to resist hydraulic loading due to overtopping.
Considerable additional engineering will be
required to define the modifications in their final form.
- Enlargement of
the Outlet Structure by extending the ogee crest and the stilling
basin by an estimated 66 m (218 ft) towards the east, so
that it will be capable of passing a flow of 1700 m3/s (140,000
cfs). This will be accompanied by enlargement and re-
shaping of the Outlet Channel to permit the increased Floodway
flow to re-enter the Red River with minimum impact on
the riverbanks. The Outlet Channel construction will be the
only component of the Floodway Expansion that will require work
on an existing
riverbank and will require measures to minimize the release of
excavated sediment into
the river flow.
- Riverbank fortification
and protection at and downstream of the Floodway Outlet, where appropriate and justifiable.

Floodway
Outlet north of Lockport on the Red River.
- Replacement of
drainage structures where necessary along the east bank of the
Floodway to accommodate the enlarged channel cross section.
Adjustment to the
capacity of these drainage structures will be possible if analysis
of their performance
since their original construction warrants it.
- Replacement of
the Inlet and Outlet structures at the Seine River Inverted Siphon
that carries riparian flows under the Floodway and release
them into the Seine River on
the west side of the Floodway. The current plan is to retain
the existing conduit under the
channel and to extend it as required to reach the new locations
of the Inlet and Outlet
Structures.
- Replacement of
the Aqueduct under the Floodway to permit the deepening and
widening of the Floodway that is planned at that location.
- Extension of a number of transmission lines that cross the
Floodway.
- Replacement of
a number of miscellaneous crossings, including gas pipelines, oil
pipelines and underground pipelines.
- Improvements
at the existing Floodway Inlet Control structure will be carried
out.
The full extent of the improvements that are required
will be addressed in the planning
phase, and may include:
- Placement of additional riprap on the downstream slopes of the
embankments adjacent to the concrete structure to protect it from
erosive
damage during the passage of large flows through the structure.
- Possible improvement of the riprap on the upstream face of the
embankments adjacent to the concrete structure to protect it
from erosive
damage during extreme events that require raising the upstream
water
level to as high as El 237 m (El 778 ft).
- Possible installation
of backup gates that could serve to control flow into
the Red River in Winnipeg during flood events if the existing
gates were
to malfunction. The justification for this will be examined
in detail in the
planning phase.
introduction / existing
floodway / need for project / options
considered / range of alternatives / proposed
floodway expansion / separate project
components / winnipeg flood improvements / recreational
facilities
Ancilliary Project Components (Under Separate Process)
City
of Winnipeg Flood Improvements
The concept for the Floodway
Expansion also includes a series of improvements to the flood
protection infrastructure within Winnipeg. The City of Winnipeg has
plans to fund improvements over the next several years to several
areas of its overall Flood Protection Works. This work will be carried
out by the City of Winnipeg with funding and timing details that have
yet to be announced. The City of Winnipeg Flood Improvements are not
considered as part of this assessment process.
introduction / existing
floodway / need for project / options
considered / range of alternatives / proposed
floodway expansion / separate project components / winnipeg
flood improvements / recreational facilities
Recreational Facilities
The proponent’s Project Description, issued in July 2003 has indicated
a desire to incorporate recreational facilities to the maximum extent
practical. Options that may be considered range from enhancement of existing
ski-hill facilities near Bird’s Hill to hiking/biking/skiing trails
along the expanded Floodway channel. Recreational use groups will be
invited to present proposals and business plans for establishment and
ongoing operation of potential new recreational facilities.
introduction / existing
floodway / need for project / options
considered / range of alternatives / proposed
floodway expansion / separate project components / winnipeg
flood improvements / recreational facilities /
|